Construction on the terminal configuration is underway. With the final removal of the last remnants of old Munck Field's runway 18/36 (replaced by a taxiway to a private hangar), the time has come to finish enhancements to the terminal. Under construction is a new 2-level boarding area, which will replace the old waiting room. Final plans as to the rearrangement of the baggage claim area are still under consideration but the new waiting area is expected to be made functional in the meantime. No changes are expected to occur to the original ticketing area and security checkpoint.
As preparation to the new terminal expansion, the old Aeromiao hangar has been relocated to the NE corner of the airfield. It is also anticipated that the rock outcropping west of the terminal will eventually be demolished.